Amsterdam,Netherlands
-
6 months
-
Confidential
-
€25,500,000
Mercury was commissioned to provide a turnkey construction service for this flagship 60,000sqft Data Centre project in Hoofdoorp, Amsterdam, the Netherlands. The project commenced in July 2016 with the phase 1 handover occurring in May 2017.
The scope of work consisted of constructing a new facility on a greenfield site with a planned IT capacity of 60,000sqft over 6 halls at a power density of 2kW/m².
The project management and execution teams compromised highly experienced Mercury management supported by both a local and international supply chain of specialist consultants, vendors and sub-contractors.