Dublin,Ireland
-
2017 - present
-
Confidential
-
€28,000,000
Following the successful closeout of CLN 1, 2 & 3 (96MW Data Centre) in December 2019, Mercury has moved on to the next phase of this Hyperscale project, for an undisclosed client on a greenfield site in County Dublin.
Mercury is carrying out the full electrical and fire protection installation on a 70MW Data Centre as part of CLN 5 & 6, which is scheduled for completion in Q1 2021.
In line with the delivery of this project, Mercury owns and coordinates the full BIM Model, alongside all other relevant on-site contractors.
Mercury’s project management and execution teams are supported by a local supply chain of specialist consultants, vendors and sub-contractors.
The scope of this project takes in two phases over the duration and presents one of the most challenging timelines we have worked on to date.