Mercury was commissioned as Main Contractor to provide the fit out of levels 4 & 5 of the TN2 Data Centre in North London. TN2 is situated on the London Docklands Campus and opened in summer 2016.
TN2 incorporates the world’s first multi-storey adiabatic cooling system, delivering an industry leading PUE of 1.16 - setting new standards in data centre efficiencies.
The 11 storey bespoke Data Centre stands at 65.9m tall, with white and associated switch rooms, battery rooms, a plant room and service corridors covering approximately 1,130m2.